Mitsubishi Chem to Delay Naphtha Cracker Maintenance

Japan's Mitsubishi Chemical said on Monday that maintenance on the No.2 naphtha cracker at its Kashima plant, with capacity to produce 453,000 tons per year of ethylene, would be delayed by about two months from its original plan of June 30.

The move comes as the company tries to replenish its petrochemical product inventories, which were depleted after its main Kashima complex was damaged in a magnitude 9.0 earthquake on March 11, a company spokesman said.

The company plans to restart the No.2 cracker around May 20 and the 375,000 tpy No.1 cracker on June 27.

The final maintenance schedule for the No.2 unit has not been set, the spokesman added.

The company had said in January that it planned to conduct maintenance on the No.2 cracker from June 30 to Aug. 17.

Free Virtual Event

Vaccine Manufacturing
Bioprocess Forum

Vaccine Manufacturing

Join global experts and innovators for a two-day virtual event exploring the latest breakthroughs and best practices in vaccine manufacturing. Discover how new technologies and process innovations are shaping the future of vaccine production, safety, and scalability.

Virtual Event

Digitalization in the Chemical Industry
CHEManager Spotlight

Digitalization in the Chemical Industry

Save the Date: October 22, 2025
The event will be promoted to a combined audience of over 100,000 professionals across Europe through the CHEManager and CITplus networks.