Mitsubishi Chem to Delay Naphtha Cracker Maintenance

Japan's Mitsubishi Chemical said on Monday that maintenance on the No.2 naphtha cracker at its Kashima plant, with capacity to produce 453,000 tons per year of ethylene, would be delayed by about two months from its original plan of June 30.

The move comes as the company tries to replenish its petrochemical product inventories, which were depleted after its main Kashima complex was damaged in a magnitude 9.0 earthquake on March 11, a company spokesman said.

The company plans to restart the No.2 cracker around May 20 and the 375,000 tpy No.1 cracker on June 27.

The final maintenance schedule for the No.2 unit has not been set, the spokesman added.

The company had said in January that it planned to conduct maintenance on the No.2 cracker from June 30 to Aug. 17.

Free Virtual Event

Digital Validation
Transforming from Paper to Digital

Digital Validation

Our experts will delve into the recently released International Society for Pharmaceutical Engineering (ISPE) Good Practice Guide: Digital Validation

CHEManager Spotlight

Standardization and Harmonization of Digital Chemical and Pharmaceutical Logistics
Creating Interfaces

Standardization and Harmonization of Digital Chemical and Pharmaceutical Logistics

CHEManager Spotlight is an exclusive event tailored for practitioners and decision-makers in the chemical industry. This part of our event series delves into the latest trends and innovations in logistics to streamline your operations and drive efficiency.